commercialhvacuk

FACTORIES & PLANT

Industrial air conditioning for factories and plant

Cooling a factory is usually a set of small, specific jobs (a control room, a panel room, a clean area, a hot machine) rather than one system for the whole building.

Industrial cooling at a glance

Usual answer
Targeted cooling, not the whole hall
Heat that air cannot fix
Radiant heat from ovens, furnaces and presses
Maximum temperature in law
None (HSE)
Fumes and dust
Capture at source with LEV; HSE says test it at least every 14 months
Explosive atmospheres
Equipment chosen for the classified zone (DSEAR)
Energy inspection
Above 12 kW; systems that only cool a process are outside the guide's intent

The short answer

Most industrial cooling is targeted: a control room, panel room, clean area or hot machine gets its own conditioned air, and the rest of the building is ventilated. The system depends on the heat source and the air, because dust, oil mist or flammable vapour can rule out an ordinary split. HSE says there is no law for a maximum working temperature, so the duties are thermal comfort and fresh air.

What does a factory or plant site actually need to cool?

On an industrial site the useful question is not how big the building is but what must stay cool, and why. Five jobs recur.

AreaWhy it is cooledUsual approachSettle early
Control room and officesPeople work there all shift and screens add heatSplit or VRF sized like any room, with filtered air to keep dust outHow hot the surrounding hall is, which changes the load
Panel and electrical roomsDrives and controllers have an ambient limit set by their makerDucted or packaged units with duty and standbyThe heat the equipment gives off, in kW, and the maker's limit
Clean production areasThe process specifies temperature, humidity or particle countAir handling unit with filtration and pressure controlThe specification from the process owner
Hot processesOvens, furnaces and presses load the hall with radiant heatCapture at source, shielding, spot cooling, air movementRadiant heat, which room cooling does little about
Hostile atmospheresDust, oil mist, solvent vapour, corrosive or flammable airSealed or filtered equipment, remote condensers, extraction at sourceWhich substances are present and whether any zone is classified

Warehouse-style sheds have their own page on warehouse air conditioning, and server and comms rooms on site follow the server room cooling requirements.

Which cooling systems are used on industrial sites?

  • Packaged units put every component in one cabinet, so there is no refrigerant pipework across the hall. They suit a roof or a yard beside a room.
  • Ducted and multi-split systems serve rooms from outdoor units placed away from dust, fumes and forklift traffic.
  • Chilled water from a chiller feeds air handling units, fan coils or machinery loops, and suits many points or a large load. The commercial chillers page covers specification; glycol loops for machinery are in the guide to process and glycol chillers.
  • Evaporative and adiabatic cooling cools by evaporating water, compared in the guide to evaporative cooling and air conditioning. HSE lists cooling towers and evaporative condensers among the most common legionella sources, so water-using designs need a risk assessment.
  • Spot cooling and air movement aim cool air or a breeze at the people or equipment that need it, as with large slow fans.

Retained Regulation (EU) 2016/2281 sets ecodesign requirements for cooling products up to 2 MW but excludes "custom-made products assembled on site, made on a one-off basis", so ask a supplier which rules a product falls under.

When is cooling the whole factory the wrong answer?

HSE says "there's no law for maximum working temperature" because in many indoor workplaces heat is "created by work activity, for example in bakeries or foundries". It adds that "air temperature alone is not a valid or accurate indicator of a comfortable workplace temperature", and that radiant temperature "will have a greater influence than air temperature on how hot the workplace will feel". A hall full of radiant heat is not fixed by chilling its air.

HSE's control measures include separating the source of heat from workers, barriers that shield them, and increased air movement. A sensible order follows from that: contain heat at its source, shield people from radiant heat, move air over them, condition the rooms where people stay for hours, and cool the whole hall only if the process requires it. For example, in a hypothetical 3,000 square metre hall with two ovens, capturing the oven heat at a hood and conditioning a supervisors' booth is a smaller and different job from cooling the hall.

What changes when the air is dusty, oily or hazardous?

Dust and oil mist foul filters and coils, so intakes sit away from the source and filters and coils need cleaning access (see filter grades and air handling units). Room cooling and general ventilation dilute contaminants; they do not capture them. HSE's ventilation guidance says it "does not cover the removal of harmful substances from the air such as welding fumes and dust generated by processes", and points to COSHH and local exhaust ventilation (LEV).

  • Oil mist. HSE's metalworking fluids guidance lists inhaling "the mist generated during machining/shaping operations" as a route of harm and names enclosures and local exhaust ventilation as controls to check and maintain.
  • LEV testing. HSE says LEV needs "a periodic thorough examination and test (at least every 14 months)", with the record kept for at least 5 years.
  • Explosive atmospheres. DSEAR requires employers to "identify and classify areas of the workplace where explosive atmospheres may occur and avoid ignition sources" in them, so equipment for a classified zone is chosen for it. See ATEX air conditioning.

Which duties apply to industrial air conditioning?

  • Fresh air. HSE quotes regulation 6: employers must ensure every enclosed workplace is ventilated by "a sufficient quantity of fresh or purified air".
  • Temperature. HSE gives no maximum, but says a minimum of "usually at least 16°C or 13°C for strenuous work" (thermal comfort), and warns that extreme process heat "can lead to serious health effects if not managed effectively" (HSE). The workplace temperature law guide goes further.
  • F-gas leak checks. GOV.UK sets at least every 12 months for 5 to less than 50 tonnes of carbon dioxide equivalent, and every 6 months for 50 to less than 500.
  • Energy inspection. The gov.uk guide applies it above 12 kW, but says it is not intended to cover systems that exist only to cool an industrial process.

How should a plant cooling brief be written?

  1. State what must be kept cool (a room, a person, a product, a machine) and the temperature and tolerance it needs.
  2. Get the heat load from equipment data: kW given off by panels, drives and machines, plus people and roof gain.
  3. List what is in the air, including dust, oil mist, solvents and any classified zone.
  4. Choose spot or room cooling, and say what happens in winter and at shutdown.
  5. Plan access for filter and coil cleaning and for the LEV and leak checks.
  6. Ask for commissioning records, as in the handover guide.

Where the answer is chilled water, the commercial chillers page explains how those systems are specified. You can send an enquiry through the form to ask for quotes against your own heat-load list.

Sources

Guides on this topic

Frequently asked questions

No. HSE says there is no law for maximum working temperature, because in many workplaces the heat comes from the work itself. Employers must still keep the temperature at a comfortable level and provide clean and fresh air, and HSE gives separate advice on heat stress in very hot processes.

Can ordinary split air conditioning go in a dusty or oily workshop?

It depends on what is in the air. Dust and oil mist foul filters and coils, so the contractor should say how the unit is protected and cleaned. Mist that people breathe is a COSHH matter to control at source with enclosures and LEV, and where an explosive atmosphere may occur the equipment must suit the classified zone.

Does an industrial air conditioning system need a five-yearly inspection?

If the air conditioning under one person's control has an effective rated output above 12 kW, the inspection duty applies in England and Wales. The gov.uk guide says it is not intended to cover systems that only cool an industrial process, so ask an energy assessor whether a given system is in scope.